Barelas Park Renovation
The City of Albuquerque Parks and Recreation Department completed Phase 1 of a major renovation of Barelas Park in the midst of one of the City’s oldest neighborhoods. With $1.8 million in federal grant funding from the Community Development Block Grant (CDBG) program, the renovation involved a complete redesign of the 3.5-acre park on 8th Street SW located between the Barelas Community Center and Barelas Senior Center.
Project Schedule
Public Input Phase Fall/Winter 2020
Design Phase Winter/Spring 2021
Construction Summer/Fall 2021
Phase 1 Completed Spring 2023
Phase 2 Coming Soon