10-26-2016 - 17-302 - Strategic Review - Albuquerque International Sunport Terminal Restroom Remodel & Change Order No. 1
Change orders to construction contracts are not uncommon. Since 2013, change orders for the Aviation Department’s construction projects, increased the average total project cost by 4.4 percent. Change order No. 1 of the AIS Terminal Restroom Remodeling Project exceeded the average and was an 82 percent increase of the original project value.