GCC Rio Grande, Inc. Tijeras Portland Cement Manufacturing Facility

GCC requests an air quality permit modification for a pound-per-hour emission increase for NOx and CO from the kilns due to operational fluctuations and a decrease in SO2 emissions.
October 03, 2023

GCC Rio Grande, Inc. submitted an application on July 12, 2023, and additional information on September 5, 2023, for an air quality permit modification to the Air Quality Program (Program) of the City of Albuquerque Environmental Health Department.

The applicant is requesting a modification to the permitted emission rates to authorize a short-term pounds per-hour increase due to operational fluctuations that may occur during the operating day. The yearly emissions will not increase.

 

Important Dates:

Comment Period Start Date: October 4, 2023

Comment End Date: November 3, 2023

Decision Due Date:  January 3, 2024

 

Related Documents

#2197-M2 Permit Application

#2197-M2 Supplemental Information

#2197-M2 Public Notice in English

#2197-M2 Aviso Publico en Espanol